Context
- Very old infrastructure
- Lack of industrial land
- High maintenance cost (average 350 million / year)
- Low draft (7 m)
CHARACTERISTICS OF THE WORK
- Construction of a 450 m long and 160 m wide mole
- Draft: 8 to 10 m
- Creation of 7 ha of land by backfilling